How long does it take to fit a bathroom?

A typical bathroom installation timeline, stage by stage, with what can make a bathroom renovation take longer and how to keep yours on schedule.

A renovated bathroom with a freestanding bath under a sash window, green glazed tiles and a walk-in shower

Quick answer

A standard bathroom refit usually takes five to ten working days. A straight swap with the same layout can take two to four days, and a full redesign or larger room ten to fourteen days or more. Allow extra time before the fit for the design visit, quote and delivery of the suite, and a little longer for wet rooms, where the waterproofing has to cure before tiling.

Straight swap
2 to 4 days
Standard refit
5 to 10 days
Full redesign
10 to 14 days or more
Bath to walk-in shower
1 to 3 days
Tiling
3 to 5 days of the total

Sources: Fradleys, MyJobQuote, MyBuilder.

Typical bathroom fitting times

ProjectTypical time on site
Replace a bath with a walk-in shower1 to 3 days (MyJobQuote)
Straight swap, same layout2 to 4 days (Fradleys)
Standard bathroom refit5 to 10 days (Fradleys)
Full redesign or larger room10 to 14 days or more (Fradleys)
Downstairs toilet1 to 2 weeks (MyBuilder)
Tiling a family bathroom3 to 5 days (MyBuilder)

Most bathroom fitters quote in working days. A standard new bathroom is usually done in one to two weeks.

Each stage of a bathroom installation

These are typical timings for a standard bathroom installation, based on Fradleys' stage-by-stage guide.

Days 1 to 2: strip-out and preparation

The old suite, tiles and flooring come out, and waste goes to the skip or tip. The fitter checks the floor, walls and pipework and fixes anything found, such as rotten floorboards.

Days 2 to 4: first fix

The plumber moves or adds pipework and wastes, and the electrician runs cables for lights, the extractor fan, a shower or underfloor heating. Walls are boarded or plastered where needed.

Days 3 to 6: tiling

Wall and floor tiles go on, then grout. In a wet room, the waterproofing goes down first and must cure before tiling starts.

Days 5 to 8: second fix

The bath, shower, toilet, basin and taps go in and are connected. The electrician fits the lights, fan and switches.

Finishing

Silicone sealing, testing for leaks, a final clean and a walk-round with you.

What can make a bathroom renovation take longer?

  • Changing the layout, such as moving the toilet, which means moving the soil pipe.
  • Hidden problems, such as rotten joists, old pipework or damp found during the strip-out.
  • Plastering, which needs drying time before tiling.
  • Wet rooms, where the tanking has to cure.
  • Complex tiling, such as herringbone or mosaic.
  • Late deliveries or a missing part.
  • New electrical circuits, which may need testing and certification.

Can I use my bathroom during the renovation?

Usually not for most of the job. If it's your only toilet, tell us at the design visit, so we can plan the order of work around it.

How long before work starts?

Allow time for the design visit, the quote, choosing your suite and tiles, and delivery. Check delivery dates for the bathroom suite and tiles before you book a start date.

How to keep a bathroom fit on schedule

  • Choose everything, down to the grout colour, before work starts.
  • Have the suite, tiles and fittings delivered before day one, and check them for damage.
  • Clear the room and the route to it.
  • Agree a fixed written price and a start and finish date.
  • Use one company for the plumbing, electrics and tiling, so the trades follow each other.

Does DIY take longer?

Almost always. Most people fit a DIY bathroom around work, so a job a fitter finishes in a week can take several weekends, and the bathroom is out of use for longer.

For a fixed timeline and price, book a free design visit. See our bathroom installation service, read about replacing a bath with a walk-in shower, or compare bathroom prices.

Planning this in Doncaster?

We fit bathroom installation across Doncaster and South Yorkshire. Every job starts with a free design visit and a fixed written price. See our bathroom installation page or call 01302 616311.

Frequently asked questions

How long does it take to fit a new bathroom suite?

A like-for-like suite swap with the same layout usually takes two to four days. A full refit with new tiles takes five to ten working days.

How long does it take to tile a bathroom?

A standard family bathroom usually takes three to five days, including preparation and grout drying time.

How long does it take to fit a wet room?

Usually one to two weeks, a little longer than a standard bathroom, because the waterproofing has to cure before tiling.

How soon can I use the shower after it is fitted?

Silicone sealant usually needs around 24 hours to cure before it gets wet. Follow the product’s instructions and your fitter’s advice.

Related services

  • Bathroom installation

    Complete bathrooms designed, supplied and fitted: strip-out, plumbing, tiling, flooring and finishing by one team.

  • Fitting only

    Already bought your suite? We fit it, including strip-out, plumbing and tiling, and check it suits the room first.

  • Bathroom design

    A free design visit in your home: we measure up, plan the layout with you and give you a fixed written price.

Get your free quote

Tell us what you need and we'll call you back to book your free design visit. Prefer to talk it through?

01302 616311
  1. 1We call you back to talk through the job.
  2. 2We visit, measure up and go through layouts and budget.
  3. 3You get a fixed written price, with no obligation.

Step 1 of 2

What do you need?

When would you like to start? Optional

Call now Free quote